Job Costing Estimate-v-Actual Worksheet

Capture estimated and actual job costs on one basis and reconcile variances without double counting.

1. Record the job and comparison basis

Job-costing worksheet header
FieldEntry
Job and customer reference____________________________
Quote and approved-scope version____________________________
Estimate date____________________________
Actual review date____________________________
Currency and tax basis____________________________
Cost allocation method____________________________
Approved changes during delivery____________________________
Reviewer and record sources____________________________

2. Capture estimate, actual and variance

Estimate-v-actual worksheet
CategoryEstimate quantityEstimate costActual quantityActual costActual โˆ’ estimateRecord source
Labour________________________________________________
Materials and consumables________________________________________________
Subcontractors________________________________________________
Equipment and access________________________________________________
Other direct cost________________________________________________
Allocated overhead________________________________________________
Total costโ€”________โ€”________________Reconciled sum
Revenueโ€”________โ€”________________Quote and billing record
Use one sign convention throughout. In this worksheet, cost variance is actual cost minus estimated cost.

Completed estimate-v-actual example

All figures are fictional user assumptions in generic currency units. The example demonstrates reconciliation, not an expected job result.

Illustrative completed rows
CategoryEstimateActualActual โˆ’ estimateSupported follow-up
Labour3,0003,600600Review added hours and rework record
Materials800950150Review quantity and supplier cost
Subcontractors6006000No variance action
Allocated overhead4004000Confirm allocation used once
Total cost4,8005,550750Reconciles to category sum
Revenue7,0007,0000Check whether added scope was approved and billed

3. Complete the review and assign action

Close-job checklist

  • Every actual figure links to a time, supplier, subcontractor or accounting record. (not complete)
  • Estimate and actual use the same categories, currency, tax and period basis. (not complete)
  • Loaded labour and overhead inclusions have been checked for duplication. (not complete)
  • Approved scope changes are separated from estimating error. (not complete)
  • Category sums reconcile to total cost and revenue records. (not complete)
  • The largest meaningful variances have a supported explanation or open question. (not complete)
  • One owner and review date are recorded for each follow-up action. (not complete)
  • The next estimate is updated only for repeatable evidence, not every one-off event. (not complete)
Follow-up action record
FindingActionOwnerReview date
________________________________________________________________
________________________________________________________________
________________________________________________________________

Related tools

Frequently asked questions

What if an actual cost record is missing?
Mark the row unresolved and obtain or reconcile the source record before closing the review. Do not silently replace an unknown actual with the estimate.
Why must estimate and actual use the same categories?
Comparable categories show where the variance arose. Reclassification can create a false category variance even when the total is unchanged.
Can this worksheet replace accounting records?
No. It is a management reconciliation built from those records. Retain the underlying documents and use appropriate accounting treatment.

Calculation methods used with this worksheet

Change history

  1. โ€” Initial public release of the article after pre-launch factual, editorial, source and presentation review.