Primary formula: protected change cost / (1 - target margin)

Educational only: Business decision support, not accounting, tax or legal advice.

Privacy: No account is required. Tool inputs and results stay in this browser. Anonymous categorical usage analytics send only governed page, tool, cluster and action identifiers; tool inputs and results are never sent. Error monitoring is disabled. Optional saved state stays only on this device.

Update policy: Reviewed when formulas or official dependencies change.

Scope: Market-neutral small-business planning using your own assumptions.

What this planner helps you decide

Best for

Construction businesses pricing incremental scope and schedule effects in a change order.

Outputs

Added direct and delay cost, contingency, required change price, retention held, initial collectible amount and revised contract value.

Start here

Enter only costs and timing effects caused by the proposed scope change.

Use a different tool when: Do not use this to compare quoted and actual job economics and identify overruns; use Job Costing & Margin Planner for that decision. Use this tool to price construction scope changes with sequencing, delay, subcontractor and retention effects.

Quote & capacity

Construction Change Order Pricing: added direct and delay cost

Added direct and delay cost, contingency, required change price, retention held, initial collectible amount and revised contract value.

Amounts use the same currency as your inputs. No currency conversion is performed.

Your industry scenario

Price incremental construction scope from site labour, materials, subcontractors, plant and travel, sequencing overhead, contingency and protected margin.

Your numbers stay in this browser

currency units

Approved ex-tax contract value before this change. Keep every amount on the same ex-tax currency basis.

currency units

Labour caused only by the changed scope. Keep every amount on the same ex-tax currency basis.

currency units

Additional materials and handling for the change. Keep every amount on the same ex-tax currency basis.

currency units

Subcontractor quotes attributable to this change. Keep every amount on the same ex-tax currency basis.

currency units

Plant, equipment and travel attributable to the change. Keep every amount on the same ex-tax currency basis.

currency units

Fixed supervision, administration or mobilisation overhead for this change. Keep every amount on the same ex-tax currency basis.

currency units

Supervision, preliminaries and site overhead extended by each delay day. Keep every amount on the same ex-tax currency basis.

Whole additional calendar or working days on the chosen project basis.

%

Rate protecting uncertainty inside the changed scope only.

%

Margin retained after incremental cost and contingency.

%

Share of the approved change-order price expected to be withheld initially.

%

Optional indirect-tax rate used only to show an inclusive price.

Industry decision result

Build a change-order amount that contains only the added scope and does not silently absorb disruption cost. Review every output on the same entered business basis.

Preparing export actionsโ€ฆ
Added direct cost
16,700.00
Schedule delay cost
2,550.00
Change contingency
1,925.00
Protected change cost
22,375.00
Required change-order price
28,685.90
Required price including tax
28,685.90
Retention held from change
1,434.29
Initially collectible amount
27,251.60
Revised contract value
508,685.90

Scenario comparison

Each row names the assumption axis changed from the baseline.

ScenarioResultDifference
Current industry scenario28,685.90Baseline
Lower Schedule delay days27,487.18-1,198.72
Higher Schedule delay days29,884.621,198.72

Save these results, change an input, then compare the updated figures with this baseline.

The baseline is temporary in this tab and is not added to shared scenario links or generated reports.

Calculation details

View calculation detailsView the formulas and inputs used for these results.

Added direct cost

Added direct costadded labour + materials + subcontractors + equipment and travel16,700 , ex tax
Result16,700.00

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Added direct costOriginal Contract Value Ex Tax
480,000
Added direct costIncremental Site Labour Ex Tax
4,200
Added direct costIncremental Materials Ex Tax
7,600
Added direct costIncremental Subcontractors Ex Tax
3,100
Added direct costEquipment And Travel Cost Ex Tax
1,800
Added direct costFixed Overhead Ex Tax
1,200
Added direct costSite Overhead Per Delay Day Ex Tax
850
Added direct costSchedule Delay Days
3
Added direct costSequencing And Delay Contingency Rate
0.1
Added direct costTarget Change Order Margin
0.22
Added direct costContract Retention Rate
0.05
Added direct costTax Rate
0

Schedule delay cost

Schedule delay costsite overhead per day * delay days2,550 , ex tax
Result2,550.00

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Schedule delay costOriginal Contract Value Ex Tax
480,000
Schedule delay costIncremental Site Labour Ex Tax
4,200
Schedule delay costIncremental Materials Ex Tax
7,600
Schedule delay costIncremental Subcontractors Ex Tax
3,100
Schedule delay costEquipment And Travel Cost Ex Tax
1,800
Schedule delay costFixed Overhead Ex Tax
1,200
Schedule delay costSite Overhead Per Delay Day Ex Tax
850
Schedule delay costSchedule Delay Days
3
Schedule delay costSequencing And Delay Contingency Rate
0.1
Schedule delay costTarget Change Order Margin
0.22
Schedule delay costContract Retention Rate
0.05
Schedule delay costTax Rate
0

Change contingency

Change contingency(added direct cost + delay cost) * contingency rate1,925 , ex tax
Result1,925.00

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Change contingencyOriginal Contract Value Ex Tax
480,000
Change contingencyIncremental Site Labour Ex Tax
4,200
Change contingencyIncremental Materials Ex Tax
7,600
Change contingencyIncremental Subcontractors Ex Tax
3,100
Change contingencyEquipment And Travel Cost Ex Tax
1,800
Change contingencyFixed Overhead Ex Tax
1,200
Change contingencySite Overhead Per Delay Day Ex Tax
850
Change contingencySchedule Delay Days
3
Change contingencySequencing And Delay Contingency Rate
0.1
Change contingencyTarget Change Order Margin
0.22
Change contingencyContract Retention Rate
0.05
Change contingencyTax Rate
0

Protected change cost

Protected change costadded direct cost + delay cost + fixed overhead + contingency22,375 , ex tax
Result22,375.00

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Protected change costOriginal Contract Value Ex Tax
480,000
Protected change costIncremental Site Labour Ex Tax
4,200
Protected change costIncremental Materials Ex Tax
7,600
Protected change costIncremental Subcontractors Ex Tax
3,100
Protected change costEquipment And Travel Cost Ex Tax
1,800
Protected change costFixed Overhead Ex Tax
1,200
Protected change costSite Overhead Per Delay Day Ex Tax
850
Protected change costSchedule Delay Days
3
Protected change costSequencing And Delay Contingency Rate
0.1
Protected change costTarget Change Order Margin
0.22
Protected change costContract Retention Rate
0.05
Protected change costTax Rate
0

Required change-order price

Required change-order priceprotected change cost / (1 - target margin)28,685.90 , ex tax
Result28,685.90

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Required change-order priceOriginal Contract Value Ex Tax
480,000
Required change-order priceIncremental Site Labour Ex Tax
4,200
Required change-order priceIncremental Materials Ex Tax
7,600
Required change-order priceIncremental Subcontractors Ex Tax
3,100
Required change-order priceEquipment And Travel Cost Ex Tax
1,800
Required change-order priceFixed Overhead Ex Tax
1,200
Required change-order priceSite Overhead Per Delay Day Ex Tax
850
Required change-order priceSchedule Delay Days
3
Required change-order priceSequencing And Delay Contingency Rate
0.1
Required change-order priceTarget Change Order Margin
0.22
Required change-order priceContract Retention Rate
0.05
Required change-order priceTax Rate
0

Required price including tax

Required price including taxrequired change-order price * (1 + entered tax rate)28,685.90 , ex tax
Result28,685.90

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Required price including taxOriginal Contract Value Ex Tax
480,000
Required price including taxIncremental Site Labour Ex Tax
4,200
Required price including taxIncremental Materials Ex Tax
7,600
Required price including taxIncremental Subcontractors Ex Tax
3,100
Required price including taxEquipment And Travel Cost Ex Tax
1,800
Required price including taxFixed Overhead Ex Tax
1,200
Required price including taxSite Overhead Per Delay Day Ex Tax
850
Required price including taxSchedule Delay Days
3
Required price including taxSequencing And Delay Contingency Rate
0.1
Required price including taxTarget Change Order Margin
0.22
Required price including taxContract Retention Rate
0.05
Required price including taxTax Rate
0

Retention held from change

Retention held from changerequired change-order price * retention rate1,434.29 , ex tax
Result1,434.29

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Retention held from changeOriginal Contract Value Ex Tax
480,000
Retention held from changeIncremental Site Labour Ex Tax
4,200
Retention held from changeIncremental Materials Ex Tax
7,600
Retention held from changeIncremental Subcontractors Ex Tax
3,100
Retention held from changeEquipment And Travel Cost Ex Tax
1,800
Retention held from changeFixed Overhead Ex Tax
1,200
Retention held from changeSite Overhead Per Delay Day Ex Tax
850
Retention held from changeSchedule Delay Days
3
Retention held from changeSequencing And Delay Contingency Rate
0.1
Retention held from changeTarget Change Order Margin
0.22
Retention held from changeContract Retention Rate
0.05
Retention held from changeTax Rate
0

Initially collectible amount

Initially collectible amountrequired change-order price - retention held27,251.60 , ex tax
Result27,251.60

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Initially collectible amountOriginal Contract Value Ex Tax
480,000
Initially collectible amountIncremental Site Labour Ex Tax
4,200
Initially collectible amountIncremental Materials Ex Tax
7,600
Initially collectible amountIncremental Subcontractors Ex Tax
3,100
Initially collectible amountEquipment And Travel Cost Ex Tax
1,800
Initially collectible amountFixed Overhead Ex Tax
1,200
Initially collectible amountSite Overhead Per Delay Day Ex Tax
850
Initially collectible amountSchedule Delay Days
3
Initially collectible amountSequencing And Delay Contingency Rate
0.1
Initially collectible amountTarget Change Order Margin
0.22
Initially collectible amountContract Retention Rate
0.05
Initially collectible amountTax Rate
0

Revised contract value

Revised contract valueoriginal contract value + required change-order price508,685.90 , ex tax
Result508,685.90

Uses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.

Construction Change Order Pricing Planner formulas โ†’
Inputs used by these formula steps
Revised contract valueOriginal Contract Value Ex Tax
480,000
Revised contract valueIncremental Site Labour Ex Tax
4,200
Revised contract valueIncremental Materials Ex Tax
7,600
Revised contract valueIncremental Subcontractors Ex Tax
3,100
Revised contract valueEquipment And Travel Cost Ex Tax
1,800
Revised contract valueFixed Overhead Ex Tax
1,200
Revised contract valueSite Overhead Per Delay Day Ex Tax
850
Revised contract valueSchedule Delay Days
3
Revised contract valueSequencing And Delay Contingency Rate
0.1
Revised contract valueTarget Change Order Margin
0.22
Revised contract valueContract Retention Rate
0.05
Revised contract valueTax Rate
0

Inputs used

Original contract value (/original contract, ex tax)
480,000
Incremental site labour (/change order, ex tax)
4,200
Incremental materials (/change order, ex tax)
7,600
Incremental subcontractors (/change order, ex tax)
3,100
Equipment and travel (/change order, ex tax)
1,800
Fixed change overhead (/change order, ex tax)
1,200
Site overhead per delay day (/delay day, ex tax)
850
Schedule delay days (whole delay days/change order)
3
Sequencing and delay contingency (decimal fraction of changed-scope direct cost)
0.1
Target change-order margin (decimal fraction of change-order price)
0.22
Contract retention rate (decimal fraction of approved change-order price withheld)
0.05
User-entered tax rate (decimal fraction of change-order price added as tax)
0
Open this calculator with preset values

This calculator supports documented, shareable scenario URLs. Compatible assistants and applications can construct links using the parameters below.

Scenario links contain only allowlisted numeric and closed-choice inputs shown in the URL; Margin101 excludes free text and identifying fields. Anyone you share the URL with can read those numbers, so do not include private or identifying data.

Example: https://margin101.com/tools/construction-change-order/?sv=1&contractRetentionRate=0.05&equipmentAndTravelCostExTax=1800&fixedOverheadExTax=1200&incrementalMaterialsExTax=7600&incrementalSiteLabourExTax=4200&incrementalSubcontractorsExTax=3100&originalContractValueExTax=480000&scheduleDelayDays=3&sequencingAndDelayContingencyRate=0.1&siteOverheadPerDelayDayExTax=850&targetChangeOrderMargin=0.22&taxRate=0

ParameterMeaningUnitAllowed valuesPresenceDefault
contractRetentionRateShare of the approved change-order price expected to be withheld initially.decimal fraction of approved change-order price withheld0 to 1Required0.05
equipmentAndTravelCostExTaxPlant, equipment and travel attributable to the change. Keep every amount on the same ex-tax currency basis.currency units/change order, ex tax0 to 10000000Required1800
fixedOverheadExTaxFixed supervision, administration or mobilisation overhead for this change. Keep every amount on the same ex-tax currency basis.currency units/change order, ex tax0 to 10000000Required1200
incrementalMaterialsExTaxAdditional materials and handling for the change. Keep every amount on the same ex-tax currency basis.currency units/change order, ex tax0 to 10000000Required7600
incrementalSiteLabourExTaxLabour caused only by the changed scope. Keep every amount on the same ex-tax currency basis.currency units/change order, ex tax0 to 10000000Required4200
incrementalSubcontractorsExTaxSubcontractor quotes attributable to this change. Keep every amount on the same ex-tax currency basis.currency units/change order, ex tax0 to 10000000Required3100
originalContractValueExTaxApproved ex-tax contract value before this change. Keep every amount on the same ex-tax currency basis.currency units/original contract, ex tax0 to 10000000Required480000
scheduleDelayDaysWhole additional calendar or working days on the chosen project basis.whole delay days/change order0 to 10000Required3
sequencingAndDelayContingencyRateRate protecting uncertainty inside the changed scope only.decimal fraction of changed-scope direct cost0 to 1Required0.1
siteOverheadPerDelayDayExTaxSupervision, preliminaries and site overhead extended by each delay day. Keep every amount on the same ex-tax currency basis.currency units/delay day, ex tax0 to 10000000Required850
targetChangeOrderMarginMargin retained after incremental cost and contingency.decimal fraction of change-order price0 to 0.99Required0.22
taxRateOptional indirect-tax rate used only to show an inclusive price.decimal fraction of change-order price added as tax0 to 1Required0

Construction Change Order Pricing: added direct and delay cost

A defensible change price includes incremental sequencing and delay effects, not direct inputs alone.

Formula summary

Primary formula
protected change cost / (1 - target margin)

Read the full methodology

Data used here

  • The estimate uses your inputs and the general business formula documented in the methodology.

Decision checks

Act on the result

Document the scope delta and supporting cost records before issuing the change order.

Stress-test the decision

Retest longer delay, higher subcontractor cost and a larger entered retention rate.

When this estimate can be misleading

  • Industry costs, tax, contract terms, capacity and targets are entered by the user; no market benchmark is embedded.
  • Use records from one consistent period and one ex-tax currency basis where money applies.
  • This is educational business decision support, not accounting, tax, legal or financial advice.
  • A defensible change price includes incremental sequencing and delay effects, not direct inputs alone.

Educational estimate, not advice. See all assumptions & limitations โ†’

Guides to interpret the decision and its assumptions.

  • Scope Change Quote Checklist

    Record and cost added work, compare absorb, partial-charge and full re-quote paths, then stop for approval.

    Read guide

Frequently asked questions

How do I price construction scope changes with sequencing, delay, subcontractor and retention effects?

Document the scope delta and supporting cost records before issuing the change order.

Which planning assumptions should I stress-test?

Compare a plausible alternative scenario and verify the decision-critical assumption that changes the plan most.