Act on the result
Document the scope delta and supporting cost records before issuing the change order.
Educational only: Business decision support, not accounting, tax or legal advice.
Privacy: No account is required. Tool inputs and results stay in this browser. Anonymous categorical usage analytics send only governed page, tool, cluster and action identifiers; tool inputs and results are never sent. Error monitoring is disabled. Optional saved state stays only on this device.
Update policy: Reviewed when formulas or official dependencies change.
Scope: Market-neutral small-business planning using your own assumptions.
Construction businesses pricing incremental scope and schedule effects in a change order.
Added direct and delay cost, contingency, required change price, retention held, initial collectible amount and revised contract value.
Enter only costs and timing effects caused by the proposed scope change.
Use a different tool when: Do not use this to compare quoted and actual job economics and identify overruns; use Job Costing & Margin Planner for that decision. Use this tool to price construction scope changes with sequencing, delay, subcontractor and retention effects.
Quote & capacity
Added direct and delay cost, contingency, required change price, retention held, initial collectible amount and revised contract value.
Amounts use the same currency as your inputs. No currency conversion is performed.
Price incremental construction scope from site labour, materials, subcontractors, plant and travel, sequencing overhead, contingency and protected margin.
Your numbers stay in this browser
Approved ex-tax contract value before this change. Keep every amount on the same ex-tax currency basis.
Labour caused only by the changed scope. Keep every amount on the same ex-tax currency basis.
Additional materials and handling for the change. Keep every amount on the same ex-tax currency basis.
Subcontractor quotes attributable to this change. Keep every amount on the same ex-tax currency basis.
Plant, equipment and travel attributable to the change. Keep every amount on the same ex-tax currency basis.
Fixed supervision, administration or mobilisation overhead for this change. Keep every amount on the same ex-tax currency basis.
Supervision, preliminaries and site overhead extended by each delay day. Keep every amount on the same ex-tax currency basis.
Whole additional calendar or working days on the chosen project basis.
Rate protecting uncertainty inside the changed scope only.
Margin retained after incremental cost and contingency.
Share of the approved change-order price expected to be withheld initially.
Optional indirect-tax rate used only to show an inclusive price.
Build a change-order amount that contains only the added scope and does not silently absorb disruption cost. Review every output on the same entered business basis.
Each row names the assumption axis changed from the baseline.
Save these results, change an input, then compare the updated figures with this baseline.
The baseline is temporary in this tab and is not added to shared scenario links or generated reports.
added labour + materials + subcontractors + equipment and travel16,700 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โsite overhead per day * delay days2,550 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โ(added direct cost + delay cost) * contingency rate1,925 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โadded direct cost + delay cost + fixed overhead + contingency22,375 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โprotected change cost / (1 - target margin)28,685.90 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โrequired change-order price * (1 + entered tax rate)28,685.90 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โrequired change-order price * retention rate1,434.29 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โrequired change-order price - retention held27,251.60 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โoriginal contract value + required change-order price508,685.90 , ex taxUses the named industry records and reports this output, ex tax. The shared engine retains full precision; display rounding never feeds the calculation.
Construction Change Order Pricing Planner formulas โThis calculator supports documented, shareable scenario URLs. Compatible assistants and applications can construct links using the parameters below.
Scenario links contain only allowlisted numeric and closed-choice inputs shown in the URL; Margin101 excludes free text and identifying fields. Anyone you share the URL with can read those numbers, so do not include private or identifying data.
| Parameter | Meaning | Unit | Allowed values | Presence | Default |
|---|---|---|---|---|---|
| contractRetentionRate | Share of the approved change-order price expected to be withheld initially. | decimal fraction of approved change-order price withheld | 0 to 1 | Required | 0.05 |
| equipmentAndTravelCostExTax | Plant, equipment and travel attributable to the change. Keep every amount on the same ex-tax currency basis. | currency units/change order, ex tax | 0 to 10000000 | Required | 1800 |
| fixedOverheadExTax | Fixed supervision, administration or mobilisation overhead for this change. Keep every amount on the same ex-tax currency basis. | currency units/change order, ex tax | 0 to 10000000 | Required | 1200 |
| incrementalMaterialsExTax | Additional materials and handling for the change. Keep every amount on the same ex-tax currency basis. | currency units/change order, ex tax | 0 to 10000000 | Required | 7600 |
| incrementalSiteLabourExTax | Labour caused only by the changed scope. Keep every amount on the same ex-tax currency basis. | currency units/change order, ex tax | 0 to 10000000 | Required | 4200 |
| incrementalSubcontractorsExTax | Subcontractor quotes attributable to this change. Keep every amount on the same ex-tax currency basis. | currency units/change order, ex tax | 0 to 10000000 | Required | 3100 |
| originalContractValueExTax | Approved ex-tax contract value before this change. Keep every amount on the same ex-tax currency basis. | currency units/original contract, ex tax | 0 to 10000000 | Required | 480000 |
| scheduleDelayDays | Whole additional calendar or working days on the chosen project basis. | whole delay days/change order | 0 to 10000 | Required | 3 |
| sequencingAndDelayContingencyRate | Rate protecting uncertainty inside the changed scope only. | decimal fraction of changed-scope direct cost | 0 to 1 | Required | 0.1 |
| siteOverheadPerDelayDayExTax | Supervision, preliminaries and site overhead extended by each delay day. Keep every amount on the same ex-tax currency basis. | currency units/delay day, ex tax | 0 to 10000000 | Required | 850 |
| targetChangeOrderMargin | Margin retained after incremental cost and contingency. | decimal fraction of change-order price | 0 to 0.99 | Required | 0.22 |
| taxRate | Optional indirect-tax rate used only to show an inclusive price. | decimal fraction of change-order price added as tax | 0 to 1 | Required | 0 |
A defensible change price includes incremental sequencing and delay effects, not direct inputs alone.
Data used here
Document the scope delta and supporting cost records before issuing the change order.
Retest longer delay, higher subcontractor cost and a larger entered retention rate.
Educational estimate, not advice. See all assumptions & limitations โ
Guides to interpret the decision and its assumptions.
Record and cost added work, compare absorb, partial-charge and full re-quote paths, then stop for approval.
Read guideDocument the scope delta and supporting cost records before issuing the change order.
Compare a plausible alternative scenario and verify the decision-critical assumption that changes the plan most.